Interconnection Cost Analysis in ISO-New England
Date Published |
06/2023
|
---|---|
Publication Type | Policy Brief
|
Authors | |
---|---|
Abstract |
Electric transmission system operators (ISOs, RTOs, or utilities) require new large generators seeking to connect to the grid to undergo a series of impact studies before they can be built. This process establishes what new transmission equipment or upgrades may be needed before a project can connect to the system and assigns the costs of that equipment. Berkeley Lab has collected interconnection cost data for 194 projects in New England from interconnection studies performed between 2010 and 2021. Project-level cost summary data are available for download on this page. We find:
|
Notes |
A brief overview of this study can be viewed here. Please join us on 29-June at 10 a.m. PT / 1 p.m. ET for a webinar discussing the results by registering here: https://lbnl.zoom.us/webinar/register/WN_f3uMo3DITpudT9d_10h0Og |
Year of Publication |
2023
|
Organizations | |
Research Areas | |
File(s) | |
Download citation |