%0 Generic %A Joachim Seel %A Joseph Rand %A Will Gorman %A Dev Millstein %A Ryan H Wiser %A Will Cotton %A Nicholas DiSanti %A Kevin Porter %D 2022 %T Generator Interconnection Cost Analysis in the Midcontinent Independent System Operator (MISO) territory %8 10/2022 %X

Electric transmission system operators (ISOs, RTOs, or utilities) require new large generators seeking to connect to the grid to undergo a series of impact studies before they can be built. This process establishes what new transmission equipment or upgrades may be needed before a project can connect to the system and assigns the costs of that equipment. Berkeley Lab has collected interconnection cost data from interconnection studies for the Midcontinent Independent System Operator (MISO), representing nearly 50% of all projects requesting interconnection from 2010 to 2020. Project-level cost summary data are available for download on this page.

We find:

Berkeley Lab will publish a series of short analytical papers of generator interconnection costs to the transmission system for MISO, PJM, SPP, ISO-NE and NYISO, which you can find at https://emp.lbl.gov/interconnection_costs