TY - GEN AU - Joachim Seel AU - Julie Mulvaney Kemp AU - Joseph Rand AU - Will Gorman AU - Dev Millstein AU - Ryan H Wiser AU - Ari Weissfeld AU - Nicholas DiSanti AU - Kevin Porter AB -
Electric transmission system operators (ISOs, RTOs, or utilities) require new large generators seeking to connect to the grid to undergo a series of impact studies before they can be built. This process establishes what new transmission equipment or upgrades may be needed before a project can connect to the system and assigns the costs of that equipment. Berkeley Lab has collected interconnection cost data for 845 projects from interconnection studies for the Southwest Power Pool (SPP) Territory. The studies were performed between 2002 and 2023 and include all of the most refined cost estimates available. Project-level cost summary data are available for download on this page.
We find:
Berkeley Lab publishes a series of short analytical papers of generator interconnection costs to the transmission system for MISO, PJM, SPP, ISO-NE and NYISO, which you can find at https://emp.lbl.gov/interconnection_costs.
DA - 04/2023 N1 -An overview of this study can be viewed here.
N2 -Electric transmission system operators (ISOs, RTOs, or utilities) require new large generators seeking to connect to the grid to undergo a series of impact studies before they can be built. This process establishes what new transmission equipment or upgrades may be needed before a project can connect to the system and assigns the costs of that equipment. Berkeley Lab has collected interconnection cost data for 845 projects from interconnection studies for the Southwest Power Pool (SPP) Territory. The studies were performed between 2002 and 2023 and include all of the most refined cost estimates available. Project-level cost summary data are available for download on this page.
We find:
Berkeley Lab publishes a series of short analytical papers of generator interconnection costs to the transmission system for MISO, PJM, SPP, ISO-NE and NYISO, which you can find at https://emp.lbl.gov/interconnection_costs.
PY - 2023 TI - Generator Interconnection Cost Analysis in the Southwest Power Pool (SPP) Territory ER -