@misc{35608, author = {Joachim Seel and Joseph Rand and Will Gorman and Dev Millstein and Ryan H Wiser and Will Cotton and Katherine Fisher and Olivia Kuykendall and Ari Weissfeld and Kevin Porter}, title = {Interconnection Cost Analysis in the PJM Territory}, abstract = {
Electric transmission system operators (ISOs, RTOs, or utilities) require new large generators seeking to connect to the grid to undergo a series of impact studies before they can be built. This process establishes what new transmission equipment or upgrades may be needed before a project can connect to the system and assigns the costs of that equipment. Berkeley Lab has collected interconnection cost data from interconnection studies for the PJM Territory, representing nearly 86% of all new unique generators requesting interconnection from 2000 to 2022. Project-level cost summary data are available for download on this page.
We find:
Berkeley Lab will publish a series of short analytical papers of generator interconnection costs to the transmission system for MISO, PJM, SPP, ISO-NE and NYISO, which you can find at https://emp.lbl.gov/interconnection_costs.
}, year = {2023}, month = {01/2023}, note = {A brief overview of this research can be viewed here.
}, }